79-81 Grosvenor Street

  • Client; Kier
  • Value; £2.4m
  • A 60 weeks programme of works on a tight site with party walls to three elevations and a retained façade to the front elevation.
  • Works include underpinning, basement excavation and construction including an attenuation tank.
  • Above ground floor a 5 storey core will be installed along with concrete to metal decking.
  • Temporary propping is required both below and above ground to retain the existing facades and party walls.