New Sutton Secondary School

  • Client; Willmott Dixon
  • Value; £6.9m
  • Largest secondary school in UK built to Passivhaus specification
  • Acting as the Principal Contractor for a duration of 24 weeks works.
  • Site set-up, enabling works inc. site haul roads, construction of pile caps for 2 no. crane bases.
  • Substructure works include underground drainage and services, RC foundations and beams, insulation, waterproofing and RC ground floor slab.
  • Superstructure works involve RC columns and 1st level RC slab. Return visit to complete external works.