79-81 Grosvenor Street
- Client; Kier
- Value; £2.4m
- A 60 weeks programme of works on a tight site with party walls to three elevations and a retained façade to the front elevation.
- Works include underpinning, basement excavation and construction including an attenuation tank.
- Above ground floor a 5 storey core will be installed along with concrete to metal decking.
- Temporary propping is required both below and above ground to retain the existing facades and party walls.