Project stats

  • Client: Sir Robert McAlpine
  • Value: £9.9m
  • Sector: Health
  • Services: Groundworks, Concrete Frames, External Works

Project Overview

JP Dunn Construction were appointed by Sir Robert McAlpine to deliver groundworks, reinforced concrete frame, and external works for a new hospital building at Tolworth.

The project followed an early works programme that included services diversions, new car parking, and access roads. The new hospital facility provides seven wards dedicated to mental health care, creating an environment designed to support recovery and well-being.

Project Details

Scope of Works
  • Utilities and services diversions

  • Development of new car parks and access roads

  • Ground beams and pile caps

  • Below-ground drainage

  • Waterproofing

  • Ground floor slabs

  • RC frame to upper floors

Working Around Live Services

Ahead of sub-base installation, operatives carefully exposed, assessed, and lowered live services including gas, water, electric, BT, and data cables. Works were undertaken by hand-digging and vacuum excavation to ensure safety and precision.

Live Hospital Environment

The hospital remained operational throughout construction. JPD implemented strict segregation measures with clear hoarding lines to separate construction activities from patient and staff areas.

  • Deliveries were restricted to avoid peak hospital times.

  • Noise and dust were carefully managed through controlled methods of working.

  • High behavioural standards were upheld at all times.